WAPA-199, RATE ORDER FY 2022

The Colorado River Storage Project Management Center (CRSP MC), proposes a new Salt Lake City Area Integrated Projects (SLCA/IP) fixed firm power rates for use December 1, 2021, through December 31, 2023.   The existing rates for these services are not set to expire until September 30, 2025; however, CRSP MC is initiating this rate action in response to a 35-percent projected increase to the firm power composite rate caused by a large increase in purchased power costs due to on-going drought conditions and a small increase to Operation, Maintenance, and Replacement (OM&R) expenses.