LAP Transmission & LAP, CRSP, & WACM BA Ancillary Services Rates

FY 2021 RATES 

(EFFECTIVE february 1, 2021 - SEPTEMBER 30, 2021)​


​**FOR DAILY, WEEKLY, AND YEARLY RATES, PLEASE CLICK ON THE FIRST BULLET TO THE RIGHT
"FY 2021 LAP TRANSMISSION AND ANCILLARY SERVICES RATES TABLE"**​

FY 2021 Transmission Rates​
Network Integration Transmission Service - L-NT1
(Attachment H to OATT)
​$74,581,196​

​Firm Transmission Service - L-FPT1
(Schedule 7 to OATT)
​$4.24 kW-month
​Non-Firm Transmission Service - L-NFPT1
(Schedule 8 to OATT)
​$5.81 MWh
$4.24 kW-month
Non-Firm Joint Dispatch Transmission Service - L-NFJDT
(Schedule 8R to OATT Attachment R)
(For the Western Energy Imbalance Service Market WEIS)
​$0.00/MWh
​​Unreserved Use Penalties - L-UU1
(Schedule 10 to OATT)
​​200% of LAP's Firm Point-to-Point rate
Non-Firm On-Peak Pricing for WestConnect - WC-8  ​​​​$12.23/MWh
$11.06/MWh
FY 2021 Ancillary Service Rates​​
Scheduling/Dispatch Service - L-AS1​
(Schedule 1 to OATT)
​$21.14 schedule/day​
​​Reactive Supply & Voltage Control - L-AS2
(Schedule 2 to OATT)
​$0.079 kW-month​
Regulation and Frequency Response - L-AS3
(Schedule 3 to OATT)

Wind Capacity Multiplier
Solar Capacity Multiplier​
​$0.205 kW-month


​148%
100%​
Energy Imbalance - L-AS4​ (CRCM SP-EI5)
(Schedule 4R and OATT Attachment R)
(Within the Western Energy Imbalance Service Market (WEIS) Footprint)

Charges shall reflect the pass-through of all the applicable charges/credits associated with the WEIS Tariff assessed to RMR for embedded load in the WACM BAA of such entity that does not make adequate alternate arrangements in the WEIS Market to satisfy its Energy Imbalance Service obligation. RMR will also charge an administrative fee to cover RMR’s cost of administering this service on behalf of such entities.

*see rate schedule for additional details

Links to Administrative Fees:  

     WEIS Administrative Fee - Feb2021 - Jan2022 Rate Year
     WAPA Administrative Fee - Feb2021 - Sep2021 Rate Year​

Generator Imbalance - L-AS9​ (CRCM SP-EI5)
(Schedule 9R and OATT Attachment R)
(Within the Western Energy Imbalance Service Market (WEIS) Footprint)

 

​​​Charges shall reflect the pass-through of all the applicable charges/credits associated with the WEIS Tariff assessed to RMR for embedded resources in the WACM BAA of such entity that does not make adequate alternate arrangements in the WEIS Market to satisfy its Generator Imbalance Service obligation. RMR will also charge an administrative fee to cover RMR’s cost of administering this service on behalf of such entities.

*see rate schedule for additional details

Links to Administrative Fees:  

     WEIS Administrative Fee - Feb2021 - Jan2022 Rate Year
     WAPA Administrative Fee - Feb2021 - Sep2021 Rate Year​

​Spinning Reserves - L-AS5​ (CRCM SP-SSR5)
(Schedule 5 to OATT)
​Pass Through
(purchase price, energy activation, plus administrative fee)
​Supplemental Reserves - L-AS6​ (CRCM SP-SSR5)
(Schedule 6 to OATT)
​Pass Through
(purchase price, energy activation, plus administrative fee)
​Balancing Authority Real Power Losses - L-AS7

​​​​4.5% - Using LAP's locational marginal price (LMP)

*see rate schedule for additional details











 




Current Year Rate Data

 Historical  Rate Data

If you have any questions, please contact Sheila Cook, Rates Manager, 

970-685-9562 or scook​@wapa.gov


 


 


 


 


 


 


 


 


 