ROCKY MOUNTAIN REGION
OPEN ACCESS
TRANSMISSION AND ANCILLARY SERVICES*
The following rates are effective October 1, 2013 – September 30, 2014
TARIFF RATES 2014
Tariff Schedule Number/Title/Rate Schedule Number | Rate * |
-Attachment H-Annual Transmission Revenue Requirement for Network Integration Transmission Service (L-NT1) | Load Ratio Share of 1/12 of the Revenue Requirement: $64,684,248 |
-7-Long-Term Firm and Short-Term Firm Point-to-Point Transmission Service (L-FPT1) |
$48.00/kW-year $4.00/kW-month $0.92/kW-week $0.13/kW-day |
-8-Non-Firm Point-to-Point Transmission Service (L-NFPT1) |
Market, NTE: $4.00/kW-month $0.92/kW-week $0.13/kW-day 5.48 mills/kWh |
Transmission Losses Service (L-AS7) |
5% Loss Rate. Transmission customers may settle financially or with energy. Pricing for this service will be WACM weighted average hourly purchase price. |
-10-Unreserved Use Penalties (L-UU1) | Penalized 200% of LAP's firm point-to-point rate, with a maximum of monthly service and a minimum of daily service. |
-1-Scheduling, System Control, and Dispatch Service (L-AS1) | $23.63 per schedule per day |
-2-Reactive Supply and Voltage Control from Generation or Other Sources Service (L-AS2) |
$0.368/kW-month $0.085/kW-week $0.012/kW-day 0.504 mills/kWh |
-3-Regulation and Frequency Response Service (L-AS3) |
$0.202/kW-month $0.047/kW-week $0.007/kW-day 0.292 mills/kWh |
-4-Energy Imbalance Service (L-AS4) |
-Imbalances less than or equal to 1.5% (minimum 4MW) of metered load settled using WACM hourly pricing with no penalty. -Imbalances between 1.5% and 7.5% (minimum 4MW to 10 MW) of metered load settled using WACM hourly pricing with a 10% penalty. -Imbalances greater that 7.5% (minimum 10 MW) of metered load settled using WACM hourly pricing with a 25% penalty. -WACM aggregate imbalance determines pricing in all bands --aggregate surplus dictates sale pricing, aggregate deficit dictates purchase pricing. |
-5-Operating Reserve - Spinning Reserve Service (L-AS5) | Long-term reserves are not available from WACM. Reserves may be provided at pass-through cost, plus an amount for administration. |
-6-Operating Reserve - Supplemental Reserve Service (L-AS6) | Long-term reserves are not available from WACM. Reserves may be provided at pass-through cost, plus an amount for administration. |
-9-Generator Imbalance Service (L-AS9) |
-Imbalances less than or equal to 1.5% (minimum 4MW) of metered generation settled using WACM hourly pricing with no penalty. -Imbalances between 1.5% and 7.5% (minimum 4MW to 10 MW) of metered generation settled using WACM hourly pricing with a 10% penalty. -Imbalances greater that 7.5% (minimum 10MW) of metered generation settled using WACM hourly pricing with a 25% penalty. - Intermittent resources not subject to 25% penalty. -WACM aggregate imbalance determines pricing in all bands --aggregate surplus dictates sale pricing, aggregate deficit dictates purchase pricing. |
-WestConnect Regional Non-Firm Transmission Service (WC-8) | -Non-firm point-to-point transmission service that utilizes a WAPA Transmission Project (TP); i.e., CAP, CRSP, LAP, INT, and PD. |