|
|
|
FEDERAL
REGISTER NOTICE Vol. 69, No. 7
From the Federal Register Online via GPO Access http://www.gpoaccess.gov/fr/index.html
DEPARTMENT OF ENERGY
Western Area Power Administration
AGENCY: Western
Area Power Administration, DOE.
ACTION: Record of Decision.
SUMMARY: Based upon the analysis and information contained in the Sacramento
Area Voltage Support (SVS) Environmental Impact Statement (EIS), the Western
Area Power Administration (Western) has decided that, should the SVS project
proceed, it should follow the configuration of the preferred alternative
described in the SVS Final EIS. This alternative is identified as Proposed
Action Option B and would consist of (1) reconductoring
a double-circuit, 230-kilovolt (kV) transmission line from Elverta
Substation to Tracy Substation, (2) constructing a new double-circuit, 230-kV
transmission line from O'Banion Substation to Elverta Substation, and (3) realigning the transmission
line near Pleasant Grove Cemetery between O'Banion
and Elverta substations and Option B of the
Cottonwood-Roseville single-circuit, 230-kV transmission line. In making this
decision, Western evaluated (1) alternatives to the proposed project, and (2)
alternatives that cover the reasonable range of options to complete
enhancements to the 230-kV power transmission system between O'Banion and Tracy substations. These transmission
enhancements and additions are necessary to maintain transmission security and
reliability. Of the alternatives evaluated, Proposed Action Option B provides
the highest degree of security and reliability for voltage support while having
relatively few environmental impacts.
FOR FURTHER INFORMATION
CONTACT: Ms. Loreen McMahon,
Environmental Project Manager, Sierra Nevada Customer Service Region, Western
Area Power Administration, 114 Parkshore Drive,
Folsom, CA 95630-4710, telephone (916) 353-4460, e-mail mcmahon@wapa.gov.
For information about the Department of Energy (DOE) National Environmental
Policy Act (NEPA) process, contact Ms. Carol M. Borgstrom,
Director, NEPA Policy and Compliance, EH-42, U.S. Department of Energy,
SUPPLEMENTARY INFORMATION: Population growth and development in the
Power system studies conducted by the Sacramento
Area Transmission Planning Group and the River City Transmission Group
concluded that transmission additions in the
Alternatives
Western identified five broad alternative
categories (new power generation, demand-side management (DSM), distributed
generation, new transmission, and transmission upgrades) in its Notice of
Intent to prepare this EIS. Between
September 12 through
The results of public
scoping meetings, workshops, meetings with agencies, and transmission system
studies contributed to identifying the alternatives carried forward for
detailed review. Alternatives eliminated from detailed review included new
power generation, DSM, and distributed generation. New power generation and
distributed generation alternatives will not solve short-term voltage support
and reliability issues. DSM would be more applicable to the distribution of
electricity, and the local utilities have implemented programs to decrease
electrical loads during peak-use hours. Western believes that in the short
term, imposing regulations of this type would not solve the reliability issues.
The alternatives carried forward for detailed
analysis included new transmission and transmission upgrades. To minimize
environmental impacts, Western incorporated standard Environmental Protection
Measures (EPM) into the project description for the Proposed Action and all
alternatives. Detailed evaluation of the Proposed Action and alternatives in
the Draft EIS considered the three types of project activities below.
1. Reconductoring would
consist of replacing the existing transmission line conductors (wires) with
higher capacity conductors. In general, the existing rights-of-way (ROW) would
be used, although some new structures may be needed.
2. New construction of transmission lines would
include designing and building new structures and installing new conductors.
New construction would occur on existing ROW where possible or require new ROW
in parallel with existing ROW.
3. Realignment would include route deviations
from Western's existing transmission lines.
The Notice of Availability (NOA) for the Draft
EIS was published in the Federal Register on
Comments to the Draft EIS prompted a minor
modification to avoid residential property. This modification affects two of
the alternatives, resulting in adding two alternatives as described in the
Final EIS. The description and impacts of the modification are identical for
both the Proposed Action and Alternative 2. The title description "Option
A" was added to the original project description of the Proposed Action
and Alternative 2. The title description "Option B" was added to the
modified alignments.
The Final EIS is an abbreviated version, which
references the Draft EIS in its entirety. The Final EIS identifies the
Preferred Alternative and provides corrections to the Draft EIS, additional
information not included in the Draft EIS, public comments, Western's responses
to those comments, and analyses of the modification applicable to the Proposed
Action and Alternative 2. Option A and Option B of the Proposed Action, as well
as the other alternatives, are described below.
Proposed Action
Option A:
This is the original alignment of the Proposed Action. It would consist of (1) Reconductoring 73.2 miles of double-circuit, 230-kV
transmission line from Elverta Substation to Tracy
Substation, (2) constructing 26.6 miles of new double-circuit, 230-kV
transmission line from O'Banion Substation to Elverta Substation, and (3) realigning the transmission
line near Pleasant Grove Cemetery, between O'Banion
and Elverta substations and 5 miles of the
Cottonwood-Roseville single-circuit, 230-kV transmission line north of Elverta Substation.
Option B:
This is the modified alignment of the Proposed Action. It would consist of (1) Reconductoring 73.2 miles of double-circuit, 230-kV
transmission line from Elverta Substation to Tracy
Substation, (2) constructing 26.6 miles of new double-circuit, 230-kV
transmission line from O'Banion Substation to Elverta Substation, and (3) realigning the transmission
line near Pleasant Grove Cemetery, between O'Banion
and Elverta substations, and 6.1 miles of the
Cottonwood-Roseville single-circuit, 230-kV transmission line. This modified
realignment of the Cottonwood-Roseville line would extend about 2 miles east of
the original alignment and then traverse south.
Alternative 1
Reconductoring Transmission Lines between O'Banion
and Tracy substations would consist of reconductoring
99.8 miles of the existing double-circuit and single-circuit, 230-kV
transmission lines from O'Banion Substation to Tracy
Substation.
Alternative 2
Option A:
New Transmission from O'Banion Substation to Elverta Substation is the original alignment of Alternative
2. It would consist of (1) constructing 26.6 miles of new double-circuit,
230-kV transmission line from O'Banion Substation to Elverta Substation, and (2) realigning the transmission
line near
Option B:
New Transmission from O'Banion Substation to Elverta Substation is the modified alignment of Alternative
2. It would consist of (1) constructing 26.6 miles of new double-circuit,
230-kV transmission line from O'Banion Substation to Elverta Substation, and (2) realigning the transmission
line near
Alternative 3
New Transmission from Elk Grove Substation to
Tracy Substation would consist of constructing 46.2 miles of new
double-circuit, 230-kV transmission line from Elk Grove Substation to Tracy
Substation.
No Action Alternative
The No Action Alternative would involve unchanged
operation of the existing transmission line system. Western would not develop
or build additional transmission lines or substation facilities in the study
area relative to voltage support.
The NOA of the Final EIS was published in the Federal
Register on
Decision
Western selected Proposed Action Option B as its
action, since it provides the maximum load-serving capability and reduces the
need for automatic generation and load curtailment during the summer peak load
periods to the greatest degree. This action best fulfills the agency's
statutory mission and responsibilities under the Central Valley Project Act
authority and it has relatively low environmental impacts.
Through analysis in the EIS,
Western determined two of the alternatives were environmentally preferable. The
No Action Alternative was determined to be the environmentally preferred
alternative with the least environmental impact. It would not, however, meet the
purpose and need. Western determined that Alternative 1 is the environmentally
preferred action alternative due to fewer environmental impacts on land use,
visual resources, and water resources compared to the Proposed Action Option B
and the other action alternatives. However, none of the action alternatives,
including Alternative 1, would avoid significant air impacts. The
environmentally preferred action alternative was not selected because its fewer
environmental impacts do not outweigh Western's need to provide maximum
load-serving capability that is provided with the selected alternative.
Proposed Action Option B
Project financing for construction is uncertain.
With this decision, Western is adopting the EPMs
outlined in the EIS. Once funding is secured, Western would complete an air
quality analysis to predict potential emissions, conduct biological and
cultural resource surveys as necessary, complete a biological assessment and
Section 7 consultation with the U.S. Fish and Wildlife Service and the National
Marine Fisheries Service, and consult with the State Historic Preservation
Office on cultural resources. Stipulations identified through these analyses
and consultations would be developed based on agreements reached between
Western and the regulatory agencies. Western would develop a mitigation action
plan (MAP) for such stipulations to ensure all practical means of avoiding
environmental harm. Western would make the MAP available to the public.
This ROD meets the requirements of NEPA as well
as the Council on Environmental Quality and DOE's
NEPA implementing regulations. Additional analyses results may affect this
decision and result in subsequent analysis or decisions. The public will be
notified of any additional activities necessary to meet Western's NEPA and
other public involvement requirements.
Dated:
Michael S. Hacskaylo,
Administrator.
[FR Doc. 04-571 Filed