RM Home About RM Contact RM Customers Environmental Review—NEPA Operations & Maintenance Planning & Projects Power Marketing Rates Loveland Area Project Firm Power Rates Transmission and Ancillary Services Rates 2012 Rate Adjustment-Transmission and Ancillary Services 2010 Rate Adjustment-Firm Power 2009 Rate Extension-Transmission and Ancillary Services 2009 Rate Adjustment-Firm Power

 

ROCKY MOUNTAIN REGION
OPEN ACCESS

Transmission and Ancillary Services*

The following rates are effective October 1, 2006 - September 30, 2007

Schedule Number and Title Rate *
- 1 -  Scheduling, System Control, and Dispatch Service (L-AS1) $27.44 per tag per day
- 2 -  Reactive Supply and Voltage Control from Generation Sources Service (L-AS2) $0.165/kW-month
$0.038/kW-week
$0.005/kW-day
0.208 mills/kWh
- 3 -  Regulation and Frequency Response Service (L-AS3) $0.220/kW-month
$0.051/kW-week
$0.007/kW-day
0.292 mills/kWh
- 4 -  Energy Imbalance Service (L-AS4) Load:  Bandwidth is +/- 5% hourly deviation (Minimum of 4 MW).  Out-of-bandwidth receives 25% penalty.  LAP real-time average sales and purchases pricing is used.

Generator:  Bandwidth is +/- 2% hourly deviation (Minimum of 4 MW).  Out-of-bandwidth receives 25% penalty.  LAP real-time average sales and purchases pricing is used.
- 5 -  Operating Reserves - Spinning Reserve Service (L-AS5) Long-term reserves are not available from WACM.  Reserves may be provided on a pass-through cost basis, plus an additional amount for administration.
- 6 -  Operating Reserve - Supplemental Reserve Service (L-AS6) Long-term reserves are not available from WACM.  Reserves may be provided on a pass-through cost basis, plus an additional amount for administration.
- 7 -  Long-Term Firm and Short-Term Firm Point-to-Point Transmission Service (L-FPT1) $32.98/kW-year
$2.75/kW-month
$0.63/kW-week
$0.09/kW-day                         
- 8 -  Non-Firm Point-to-Point Transmission Service (L-NFPT1) Market, NTE:
$2.75/kW-month                       
$0.63/kW-week
$0.09/kW-day
3.75 mills/kWh
- 9 - Transmission Losses Service (L-AS7)  Current Loss Rate: 5%
Transmission customers may settle financially or with energy.  Pricing for this service will be LAP weighted average hourly real-time purchase price.
Attachment H
Annual Transmission Revenue Requirement for Network Integration Transmission Service (L-NT1)
Load Ratio Share of 1/12 of the Revenue Requirement:  $39,272,990

* The Open Access rate methodologies are effective through February 28, 2009 with the exception of
Schedule 3 - Regulation and Frequency Response Service, which is effective through May 31, 2011

 

 

 

About Power Marketing Transmission Newsroom Business Policies
Products Plan contents OASIS News features Careers No FEAR act
Organization chart Plan processes Functions News releases Doing business Privacy policy
History General power contract provisions OATT Revisions Fact sheets Energy Services Accessibility
Financial information Rates and Repayment Interconnection Publications EPTC Adobe PDF
Power projects EPAMP Infrastructure projects   Federal Register Notices  
Customers Legislation/Regulation     Regions  
Defining the future IRP     FOIA  
Industry participation Hydro Conditions     Industry links  
  Drought